Start with the door layout
Record the structural opening width and height, required clear opening, number of moving leaves, fixed side panels, opening direction and available storage space. A single sliding leaf, bi-parting pair, telescopic arrangement and swing leaf use different geometry even when the clear passage looks similar.
Measure the header, ceiling, side pocket, floor level and nearby walls. Identify glass, framed, timber, metal or composite leaves and note the estimated finished mass rather than the bare-panel mass. Handles, decorative cladding and seals change the final load.
Separate activation, safety and access control
Activation devices request an opening; safety devices monitor the travel or threshold; access-control devices decide who may enter. These functions should not be treated as one sensor. A project may combine radar or presence sensing, safety beams, push buttons, card readers, face terminals, electric locks and a fire signal.
Write the required behavior for normal entry, authorized entry, exit, hold-open, locked mode, fire alarm, power loss and manual release. The controller interface must be checked against that sequence before wiring starts.
Installation interfaces that affect reliability
| Interface | Confirm before installation | Acceptance evidence |
|---|---|---|
| Support | Header strength, fixing points, level and access for service | Fixing record and alignment check |
| Door leaf | Finished mass, hangers, bottom guide and edge details | Leaf data and full-travel test |
| Electrical | Supply, isolation, cable routes and earthing interface | Wiring record and functional test |
| Finishes | Covers, glass, frames, ceiling closure and protection | Visual inspection and snag list |
Commissioning is a sequence, not a speed setting
First move the leaf manually where the equipment permits and check for rubbing, uneven guides or blocked travel. Then verify the mechanical installation, controller wiring and sensor zones. Run learning or setup procedures for the actual model, test low-risk operation, and only then confirm the required opening and closing behavior.
Acceptance should cover repeated cycles, approach from different directions, threshold occupancy, obstruction response, lock release, selected operating modes and power-loss recovery. Record the model, settings and any site-specific limitation.
Information to send for selection
- Dimensioned opening and elevation drawing
- Moving-leaf count, construction and finished mass
- Clear opening and available side/header space
- Indoor, sheltered or exposed installation conditions
- Traffic pattern and accessibility requirements
- Sensors, access control, locks and fire interface
- Power supply and cable responsibility
- Destination, quantity, packing and document requirements